Setting an asset's technical end date as start date of activity
You can set the expected technical end date of an asset as the start date of an activity definition
With this setting, the start date of activity definitions of the Replacement activity type can be based on the expected technical end date of their linked asset, when compiling a maintenance plan. If you do not select the expected technical end date as start date of this type of activity definition, the expected economic end date is used to determine the start date.
* 
For more information on activity types and compiling maintenance plans, refer to the Maintenance Manager part of the user documentation.
Procedure
1. Go to Field definer > Business Objects selection level, select the Base activity definitions business object.
2. On the Status transitions action panel, select the Under construction option.
3. On the System business objects action panel, select the Business objects settingsoption.
4. The Maintenance activity definition settings dialog box is displayed.
5. If you want to base the start date of maintenance activity definitions on the expected technical end date of their linked assets, select Yes in the Expected technical end date field, in the Set expected technical end date of asset as start date of activity definition section.
6. Click Save.
7. Click Exit.
8. Return to the Business objects selection level and on the Status transitions action panel select Completed.
The set value is now applied to the start date-times of activity definitions of the Replacement activity type when compiling maintenance plans in the Maintenance Planner TSI.