Core TSIs : Surveys : Condition Surveys : Working with Condition Surveys : Modifying existing survey data
Modifying existing survey data
Prerequisites
To be able to modify the survey data of an existing survey, the survey must be in either the In preparation, In progress – in Planon or the Ready for tuning status.
Procedure
1. Go to Survey Projects.
2. Select the survey project you want to modify and go to Surveys.
3. Select the survey and the status you want to assign to it.
4. A warning message appears when you change the survey status.
5. Click Proceed.
The outdated condition data and condition details linked to the survey are deleted from the Assets TSI.
1. If a maintenance plan already exists whose activity definitions refer to this survey’s asset condition details, an error message appears.
2. Click Cancel.
3. In Maintenance planner, manually delete the associated activity definitions from the maintenance plan.
4. In Condition Surveys, select a relevant status. The survey status is modified. You can now edit the survey project data.
* 
If orders were already generated for the activity definitions, you cannot change the survey data.