The extent to which a survey has been carried out.
In Surveys TSI, you can assign various statuses to a survey:
In preparation
In progress – checked out
In progress – in Planon
Ready for tuning
Ready for processing
Processed. This final status cannot be selected. It is assigned automatically after the Process survey data action is completed.
These statuses are selected at the Surveys selection level > Status transitions action menu. The In progress – checked out status is assigned to a survey whose survey data is exported to an external surveying tool. To use the action Process survey data a survey must be set to the status Ready for processing.
* 
To make a status transition to Ready for processing the Observed condition before maintenance field at Survey elements must be populated.
* 