WBS item status
The status of a WBS item indicates the extent to which a task has progressed in the project. WBS items can have the following statuses: In preparation, In progress and Completed.
When the status changes to In progress or Completed, Planon performs a dependency check. See the following table for more information.
Status change
Dependency check
In preparation > In progress or Completed
If a WBS item has predecessors with an FS dependency and a time interval not less than 0, the status should be Completed. Otherwise, Planon displays an error message.
If a WBS item has predecessors with an FS dependency and a time interval less than 0, the status should be Completed. Otherwise, Planon displays a warning message.
In preparation > In progress or Completed
If a WBS item has predecessors with an SS dependency and a time interval less than 0, the status should be In progress or Completed. Otherwise, Planon displays a warning message.
If a WBS item has predecessors with an SS dependency and a time interval not less than 0, the status should be In progress or Completed. Otherwise, Planon displays an error message.
In progress > Completed
If a WBS item has predecessors with an FF dependency and a time interval less than 0, the status should be Completed. Otherwise, Planon displays a warning message.
If a WBS item has predecessors with an FF dependency and a time interval not less than 0, the status should be Completed. Otherwise, Planon displays an error message.
In progress > In progress or Completed
If a WBS item has predecessors with an SF dependency and a time interval less than 0, the status should be In progress or Completed. Otherwise, Planon displays a warning message.
If a WBS item has predecessors with an SF dependency and a time interval not less than 0, the status should be In progress or Completed. Otherwise, Planon displays an error message.