Field | Description |
---|---|
Predecessor | Enter a WBS item to precede the WBS item currently selected. This field is mandatory. |
Successor | Specifies the WBS item succeeding the currently selected WBS item. |
Dependency type | Enter one of four dependency types for the currently selected WBS item: Start-to-finish, Finish-to-start, Start-to-start and Finish-to-finish. |
Time interval | Enter a time interval using the dialog box that you can open in this field. By default, the interval is 0. Enter a negative value to create an overlap between start dates or end dates of the respective WBS items. |
Has conflict | Displays if this dependency has a planning conflict with a WBS item. The default value of this field is F (false). If the dependency causes a conflict in planning a WBS item, the value of this field automatically changes to T (true). |