Constraint Category | Constraint type | Description |
---|---|---|
Flexible | None | This constraint type indicates that a WBS item can start as soon as possible. This is a default constraint type applied to all new WBS items when they are scheduled from the project start date. |
Semi-flexible | No earlier than | When this constraint type is set, the WBS item can start or finish on or after the specified constraint date. This is a default constraint type if a constraint start or end date-time is entered. |
No later than | This constraint type indicates that a WBS item can start or finish on or before the specified constraint date. | |
Inflexible | On (No later than, No earlier than) | This constraint type indicates that a WBS item must start or finish on the specified constraint date. |