If you want to make a comprehensive duplicate of an asset activity definition in an asset service plan, use the following procedure:
Procedure
1. Go to Activities/registrations > Asset activity definitions.
2. Select the asset activity definition you want to deep copy.
3. On the action panel, click Deep copy.
4. In the Copying dialog box, select the relevant options to copy along one or more types of expected costs.
5. Click OK.
6. If relevant, make adjustments to the data of the deep copy, for example the Description.
If available, the following elements are included in the deep copy:
The selected expected costs
Linked schedule
* 
If you only want to make a simple copy of the asset activity definition – that is excluding the linked schedule or expected costs - select the Copy option on the action panel instead of the Deep copy option.