Adding multiple work assignments in Resource Planner
With the Work assignments license, you can add one or multiple work assignments to a single order in Resource Planner:
1. In Resource Planner, orders are shown in the Unplanned orders panel at the bottom. By moving them to the planboard, a work assignment is created (status is Planned).
2. To create another work assignment for the same order, press CTRL and simultaneously drag-and-drop the work assignment to the required place on the planboard.
3. Drop it onto:
◦ the same resource and a different time slot
◦ a different resource and to the same / another time slot
You have 'cloned' the work assignment.
4. Optional: right-click the work assignment to open a context menu. The options Edit work assignment and Key work assignment? enable you respectively to edit the work assignment fields and mark the assignment as a key work assignment.
To edit the corresponding order, double-click the work assignment on the planboard.
For more information, see
Work assignment fields.