Adding work assignments in Work Orders
You can add multiple work assignments to an order in Work Orders . For information on the work assignment concept, see Work assignment.
Procedure
1. In Work Orders , select an order for which you want to create work assignments and go to Work order details.
* 
If the order includes suborders to which you want to link work assignments, select the relevant suborder and drill down to Order details > Work assignments.
2. On the Work assignments action panel, click Add.
* 
To create multiple work assignments, you can either copy the work assignment and modify its details, or you can add a new work assignment.
3. On the data panel, fill in the work assignment data.
For more information, see Work assignment fields.
4. With each new work assignment, decide whether to allocate it to:
the same Internal tradesperson and a different Start-date-time
a different Internal tradesperson and the same / another Start-date-time
5. Click Save.
The work assignment is added in the Planned status. From here on, it will go through the configured workflow. The status of the key work assignment will automatically update the status of the order.
* 
For information on configuring status mapping between order and work assignment see Status mapping