Status transitions during synchronization
When applying a status transition to the work assignment (which will update the order status), the Planon application will attempt to apply a transition based on the (alphabetical) order of the code of the statuses available in Business object settings (same is true for Actions <-> Reasons).
Example
An order in status O1 can go to the following Assigned statuses:
Status from
Status to
<empty>
O1
O1
O2
O1
O3
When applying a status transition in Resource Planner to work assignments, the order status (when synchronized) will go from O1 to O2 rather than O3. That is because:
The transition is possible.
Code O2 comes before O3.