Adding/modifying schedules
You can add schedules by following this procedure.
Procedure
1. Go to Work plans > Activities.
2. Select an activity for which you want to add / modify the schedule.
* 
If the schedule is already Active, you must first select the Under construction action on the action panel.
3. In the Schedule field, select a relevant schedule and click OK.
4. Or, to add a new schedule, click Add in the Schedule dialog box.
5. Enter a Code, Name and Frequency for the new schedule.
You can choose Daily, Weekly, Monthly or custom Calendar options for the schedule's intervals.
6. Click Save and OK.
You have added / modified the schedule for the selected activity. You can activate the schedule by selecting the Active action on the action panel.