Core TSIs : Projects : Working with Projects : Working with a WBS item on the graphical planner
Working with a WBS item on the graphical planner
You can extend or shorten the effort of a WBS item on the graphical planner.
On the toolbar to the left of the graphical planner, set the drag & drop period by a measure of hours, days, weeks for extending or shortening a WBS item. This will override the units specified for Effort.
When a WBS item is extended or shortened on the graphical planner, the Effort is modified accordingly.
In Planon ProCenter , you can only extend or shorten a WBS item but not a summary WBS item.
Procedure
1. Go to Project items > WBS items.
2. Select the Graphical planner tab.
3. Select a WBS item.
4. On the graphical planner, hover on the WBS for the extend cursor Image of a double arrow.
Drag the either ends of the WBS item to extend or shorten the effort. Based on the drag&drop unit specified on the toolbar, the appropriate changes are applied to the effort.