Core TSIs : Projects : Working with Projects : Rescheduling WBS items with dependencies
Rescheduling WBS items with dependencies
If you change the planned start date or end date of a WBS item with a dependency, the start and end dates of successor WBS items will also change or dependencies will be removed.
* 
If the Planned start date-time of a WBS item is changed, the successor in the dependency is rescheduled in all 'start-to-finish' and 'start-to-start' dependencies in which the changed WBS item is the predecessor. Similarly, if the Planned end date-time is changed, then the successor in the dependency is rescheduled in all 'finish-to-start' and 'finish-to-finish' dependencies in which the changed WBS item is the predecessor.
Example 1:
WBS item 1 lasts two days longer than anticipated. Consequently, both WBS item 2 and WBS item 3 start two days later.
Example 2:
WBS item 1 is finished two days earlier. There is a five-day 'finish-to-start' (FS) dependency with WBS item 2 and a three-day FS dependency between WBS items 2 and 3. Due to the early completion of WBS item 1, both WBS item 2 and WBS item 3 start two days earlier.
Example 3:
WBS item 3 was planned on 01/13 but now gets a constraint start date (01/11). The planned start date changes from 01/13 to 01/11 and the end date from 01/15 to 01/13. This creates a planning conflict of the 'finish-to-start' dependency with predecessor WBS item 2. The FS dependency between WBS item 1 and WBS item 2 does not change. WBS item 4 is rescheduled, it starts two days earlier.
Note the following:
If the planned start date time of a WBS item is changed, this change will be displayed in the Start date-time field of every linked order.
If a main order is linked to a WBS item, the suborders that are not linked to a WBS item are rescheduled together with the main order. The suborders that are directly linked to a WBS item are rescheduled via the WBS item and not via the main order.
The orders with the status Planned, Completed or Closed will not be rescheduled, but the WBS item to which they are linked will be rescheduled.
* 
Time zones are not taken into account in project planning when calculating planned date-times. Example: WBS item 1 is linked to a property in the United Kingdom (UK) and WBS item 2 is linked to a property in the Netherlands. WBS item 2 can start when WBS item 1 has been completed. The planned start date-time of WBS item 2 becomes the planned end date-time of WBS item 1. If time zones were taken into account, the planned start date-time of WBS item 2 would be one hour later because the time zone of the Netherlands is GMT + 1.