Core TSIs : Projects : Working with Projects : Adding a WBS item
Adding a WBS item
You can break down the selected project into mutually dependent items of work (WBS items).
Procedure
1. Go to Project items > WBS items
2. On the action panel, click Add.
3. In the data panel, complete the relevant fields.
For a description of these fields, see WBS item fields.
4. Click Save.
By default, the effort of a WBS item is one working day.
When a WBS item is registered for a project, the project calendar is taken into account to determine the start date-time of the WBS item. If no project calendar is defined, Planon will start the WBS item at the beginning of the day, which is 00:00 hours. When starting a (sub)project, if the project calendar differs from the property calendar, Planon will prompt you to decide whether the property calendar should be copied to this project.