Maintenance regime is condition-based
You selected a condition-based maintenance regime. The Enter values dialog box appears.
Procedure
1. In the Asset condition details field, select the latest condition details associated to the asset.
2. From a period-picker that is available in the Deterioration period field, select a period of time to which the deterioration curve applies.
3. From the period-picker in the Min. period between activities field, select the shortest distance in time to be scheduled between activities.
4. Click OK.
Depending on the entered values, one or more maintenance activities are now scheduled for the selected activity definition.