Viewing generated maintenance orders
It is possible to view the maintenance orders generated from recurring or non-recurring activities.
Procedure
1. Go to Work Orders .
2. At Properties, select the property whose orders you want to view.
3. At Orders, view the elements list.
The maintenance orders that you generated are available in the elements list. Any expected costs that are linked to the activity definition are copied to the maintenance order’s estimates and order lines.
* 
You can only delete maintenance orders with a Canceled status. If you delete a maintenance order, then the corresponding maintenance activities (in Maintenance Planner > Definitions & schedules > Activity definitions > Maintenance activities) are also deleted.
For Fixed completion method activity definitions, you can only delete the last maintenance activity.
* 
In Work Orders you can add suborders to a generated maintenance order.
* 
For maintenance activities that are deactivated in the graphical planner, no maintenance orders are generated.
For maintenance activity definitions that are linked to contracts with the Blocked status, no maintenance orders are generated.
After maintenance orders are generated, the linked schedule can no longer be changed.
If the start date-time of a recurring activity coincides with the start date-time of a non-recurring activity within the same activity definition, a maintenance order is generated for the recurring activity only. The non-recurring activity is deleted.