You can partly replace an existing schedule of a selected activity definition.
This feature is available for the activity definitions that exist in a compiled maintenance plan. You can replace the schedule of a selected activity definition in Maintenance Planner > Definitions & Schedules.
Procedure
1. At Definitions & Schedules, select the activity definition whose existing predictive-based schedule you want to replace.
2. On the action panel, click Schedule predictive-based activities.
3. In the Predictive-based schedule dialog box, make the relevant changes.
The schedule cannot be replaced if maintenance orders are already generated.