Deleting maintenance activities from clustered orders
It is possible to delete maintenance activities from clustered orders, in case there was a mistake at the time of generating the maintenance order. The deleted maintenance activity will again be added in the next order generation phase.
This feature is useful to complete the maintenance orders in time.
Procedure
1. On the Maintenance plan > Definitions & schedules > Details, select the maintenance activity(-ies) you want to delete.
2. On the action panel, click Delete.
◦ The activity must have the Canceled status.
◦ More than one maintenance activity must be linked to the clustered order.
| If you delete a maintenance activity that is based on a maintenance activity definition with costs, the related order lines are also deleted. |