Deep copying a standard activity definition
You can make a comprehensive duplicate of a standard activity definition in a standard service plan.
Procedure
1. Go to Maintenance Library > Standard activity definitions.
2. Select the standard activity definition you want to deep copy.
3. On the action panel, click Deep copy.
In the Copying dialog box, select the expected costs and / or checklist items that you want to include in the deep copy.
4. If required, modify the copy’s data, such as its Description.
The standard activity definition is copied. The following elements are included in the copy:
Selected expected costs;
If selected: checklist items;
Linked schedule.
* 
If you only want to make a regular copy of the standard activity definition – that is excluding linked schedule or expected costs - select the Copy option in the action panel instead of the Deep copy option.