Core TSIs : Planned Maintenance : Work balancing in the graphical planner : Adding non-recurring activities in the graphical planner
Adding non-recurring activities in the graphical planner
You can add individual, non-recurring maintenance activities and facilitate easy scheduling and rescheduling of these maintenance activities in the graphical planner.
* 
You cannot add an activity manually for the activity definitions with a Fixed completion scheduling method.
Procedure
1. Go to Maintenance Planner > Definitions & schedules.
2. Click the Graphical planner button.
3. On the graphical planner, point to the time line of the activity definition to which you want to add a non-recurring activity.
4. Right-click the date-time where you want to add a non-recurring activity.
5. Click Add activity.
A non-recurring activity is added to the graphical planner. You can now generate a maintenance order from this activity.