Extending or shortening individual contract lines
You can extend or shorten the duration of individual contract lines by changing the contract line’s end date.
Procedure
1. At the Contract lines selection step, select the contract line you want to extend or shorten.
2. On the action menu, click Change end date.
The Enter values window is displayed. By default, the current end date is selected in the End date field.
3. In the Enter values window, click Icon depicting a calendar in the End date field to select another end date.
* 
If you clear the End date field of the Enter values window, the contract line’s End date field is cleared too.
4. Click the required date and click OK.
The contract line’s end date has now been changed.
* 