Item | TSI/FC | Calculations |
---|---|---|
Original budget | TSI/FC | Budget.Inital amount |
Modifications | TSI/FC | Approved budget changes + Approved budget transfers |
Actual budget | TSI/FC | Original budget + modifications |
Commitments | FC | Expected costs + invoiced costs |
Available budget | TSI/FC | Actual budget – (commitments + reserved budget size) |
Forecast to go | FC | Active forecasts to go |
Forecast end of work | TSI/FC | Commitments + forecasts to go + reserved budget size |
Balance | TSI/FC | Actual budget - forecast end of work |
Payments | TSI/FC | Invoiced costs |
Payments to do | TSI/FC | Expected costs |
Open amounts to pay | TSI | Expected costs (field will be canceled) |
Estimated costs | TSI | Estimated costs |