The following table describes the formulas for calculating the various budget scenarios in Capital Project Management:
Item
TSI/FC
Calculations
Original budget
TSI/FC
Budget.Inital amount
Modifications
TSI/FC
Approved budget changes + Approved budget transfers
Actual budget
TSI/FC
Original budget + modifications
Commitments
FC
Expected costs + invoiced costs
Available budget
TSI/FC
Actual budget – (commitments + reserved budget size)
Forecast to go
FC
Active forecasts to go
Forecast end of work
TSI/FC
Commitments + forecasts to go + reserved budget size
Balance
TSI/FC
Actual budget - forecast end of work
Payments
TSI/FC
Invoiced costs
Payments to do
TSI/FC
Expected costs
Open amounts to pay
TSI
Expected costs (field will be canceled)
Estimated costs
TSI
Estimated costs