Core TSIs : Activity planner : Working with Activity planner : Generating orders for planned activities
Generating orders for planned activities
A process of generating orders for planned activities aimed to improve efficiency and flexibility. By focusing on specific planning details, this task allows for the immediate initiation of work orders, ensuring scheduled tasks are executed on time.
Procedure
1. Go to the Activity planner TSI > Activity definitions selection level.
2. Click Activity definitions and select the required activity definition to which you want to generate orders.
3. On the action panel, click Generate orders.
The Enter values pop-up opens.
4. Select an appropriate Start date-time and End-date time for the order generation and click OK.
PPM orders are generated in the Orders TSI.